Ex. AGY-AVIATION-SURFACE-049 Order Primary source read

Port of Seattle temporary suspension of approximately 20 construction projects (Apr. 9-13, 2020) pending review of contractors' COVID-19 jobsite safety plans (announced Apr. 8, 2020)

Port temporarily suspends ongoing construction to review COVID-19 safety plans

Port of Seattle (Executive Director) · Port of Seattle (Washington municipal corporation) (County)

The COVID Project

The record

Jurisdiction
Port of Seattle (Washington municipal corporation) · Washington
Level
County
Authority
Port's contractual and proprietary authority over its construction projects; implementation of Governor Inslee's Proclamation 20-25 construction limits
Issued
2020-04-08 Apr. 8, 2020
Effective
2020-04-09
End
2020-04-13 (resumption conditioned on approved safety plans) (read as 2020-04-13)
In force
Apr. 9, 2020 to Apr. 13, 2020
Quarters
2020 Q2
Limitation types
Business closureWorkplace rules
Addressees
  • contractors and subcontractors on approximately 20 Port construction projects (SEA airport and maritime)
Functions reached
  • JS job sites shut down and reopened only under approved COVID-19 safety plans
  • SB subcontractors and trades
  • OW owner-agency project suspension
Collection
Aviation and surface-transport regulators AGY-AVIATION-SURFACE

Operative words

"The Port of Seattle will temporarily suspend approximately 20 current construction projects from Thursday, April 9 to Monday, April 13 to complete reviews and updates of contractors' jobsite safety plans, an action necessary to protect workers and slow the spread of the COVID-19 virus. The temporary suspension does not apply to Northwest Seaport Alliance projects. The Port required all contrac[tors to submit COVID-19 safety plans]...."

Enforcement

suspension of work under Port contracts; Governor's Proclamation 20-25 enforcement

Notes

Owner-agency construction suspension reaching contractors and trades on airport and port projects; a compelled modification of construction operations (site safety plans) in Q2 2020.