The record
- Jurisdiction
- City of Boston, Massachusetts · Boston · Massachusetts
- Level
- City
- Authority
- BPHC Order Establishing Supplemental COVID-19 Restrictions (Ex. 010)
- Issued
- 2020-12-14 Dec. 14, 2020
- Effective
- 2020-12-16
- End
- 'for at least three weeks'; extended Jan. 5, 2021 (Ex. 016) (read as 2021-01-05)
- In force
- Dec. 16, 2020 to Jan. 5, 2021
- Quarters
- 2020 Q42021 Q1
2020 Q22020 Q32020 Q42021 Q12021 Q22021 Q3
- Limitation types
- Business closureCapacity limitGathering cap
- Addressees
- Boston businesses and residents
- Functions reached
- Collection
- Boston MET-BOS
Operative words
effective Wednesday, December 16, the City of Boston will return back to a modified Phase Two, Step Two of the Reopening Massachusetts plan... Mayors and city leaders from Massachusetts are joining Boston in announcing similar restrictions in their cities and towns, including Arlington, Brockton, Lynn, Newton, Somerville, and Winthrop.... The City of Boston had been in Step One of Phase Three of the Reopening Massachusetts plan since July 6, 2020.... The following industries in the City of Boston are required to close starting Wednesday, December 16 for at least three weeks: Indoor fitness centers and health clubs... Movie theaters; Museums; Aquariums; Indoor recreational and athletic facilities (except for youth 18 and under)... Sightseeing and other organized tours (bus tours, duck tours, harbor cruises, whale watching); Indoor historical spaces & sites; Indoor event spaces...; Indoor and outdoor gaming arcades
Enforcement
Notes
Names the six other municipalities that joined Boston's rollback (Arlington, Brockton, Lynn, Newton, Somerville, Winthrop); cites positivity 7.2 percent and 90 percent adult non-surge ICU occupancy.