- Jurisdiction
- United States (Pennsylvania LNG facility)
- Level
- Federal
- Authority
- Natural Gas Act § 7; 18 C.F.R. 157.20; certificate order of Apr. 15, 2019
- Issued
- 2020-10-08 Oct. 8, 2020
- Effective
- n/a (notice) (read as 2020-10-08)
- End
- Requested extension to June 2021 (read as 2020-12-31)
- In force
- Oct. 8, 2020 to Dec. 31, 2020
- Quarters
- 2020 Q4
2020 Q22020 Q32020 Q42021 Q12021 Q22021 Q3
- Limitation types
- Other
- Addressees
- UGI LNG, Inc.; interested persons
- Functions reached
- PL pipeline and LNG construction schedules
- Collection
- Mining, Oil and Gas, and Energy Services SEC-23
Operative words
UGI states that it submitted its [initial request for notice to proceed]... [delayed] construction activities until late June [2020]... Novel Coronavirus Disease (COVID-19) pandemic.... UGI now belatedly requests an additional nine months, or until June [2021] to extend its certificate authorization.
Enforcement
Commission action on the extension under delegated authority
Notes
One of a series of FERC extension-of-time notices in 2020-2021 reciting COVID-19 construction delays (Transcontinental Gas Pipe Line Aug. 26, 2020 and Mar. 26, 2021; Columbia Gas Transmission June 5, 2020; Texas Gas Transmission Dec. 21, 2020; Equitrans Oct. 1, 2020; Rockies Express Nov. 3, 2020; Eastern Gas Transmission Aug. 11, 2020 and Feb. 1, 2021; National Grid LNG Feb. 12, 2021; Spire STL June 24, 2021; Spire Storage West Apr. 1, 2021; Total Peaking Feb. 1, 2021; RH energytrans Feb. 1, 2021), located in the Federal Register API and not saved.
Retrieval noteFR Doc. 2020-22296; 182797 bytes; bracketed words fill extraction breaks.